Water Dam System Steel Pipe Installation
December 1, 2022China Sewage Project
April 20, 2022
Aim of the project
- To establish a new and effective sewage rationalization works at Kuching, Sarawak which will reduces the pollution loading into the receiving water courses.
- To connect pipelines for waste water by using Manshield Excavation Method.
Scope of works
- Duration of project: (2021)
- Sizes of pipe jacking involved: ∅1500mm
- Total Span Distance: 186m
- Type of jacking method: Manshield Excavation Method