Aim of the project
- To install 2200mm Steel Pipes for Water Damping System from the valve door of the damping system to the flow outlet.
- To control water volume flow in order to prevent flood.
- To establish new piping system which is cost effective in term of operational and maintenance wise.
Scope of works
- Duration of project: (2020 - 2022)
- Sizes of pipe jacking involved: ∅2200mm
- Concrete Base for pipe installation with proper level.
- Steel Pipe Casted with concrete base on the design specification.