Aim of the project
- To establish a new and effective sewage rationalization works at Jiaxing, China which will reduces the pollution loading into the receiving water courses.
- To connect and install 2200mm waster water pipeline.
Scope of works
- Duration of project: (2019)
- Sizes of pipe jacking involved: ∅2200mm
- Total Span Distance: 1.86km
- Type of jacking method: Tunnel Boring Maching Excavation & 2200mm Sewage Pipeline Installation